Alstom/ABB, GT13E, 1978, 600 MW, Combined Gas and Steam Turbine Power Plant

Description

  1. Overview
    1. Plant has very few operation hours
    2. Consists of one direct fired boiler installation, heavy fuel oil (HFO) and gas, and a steam turbine in combination with a gas turbine
    3. Boiler and steam turbine were commissioned in 1978
    4. In 1988 the GT13E gas turbine has been taken into operation
    5. New EV burner unit installed in 1996
    6. New and modern digital control system installed several years ago
  2. Gas Turbine Specifications
    1. Manufacturer: Alstom/ABB, model GT13E
    2. Capacity: 150,000 kW (150 MWe / 18.5 MVA, cos phi 0.8)
    3. Frequency: 50 Hz
    4. Year: 1988
    5. Speed: 3000 rpm
    6. Fuel: Gas
    7. Last C-inspection: 2004
    8. Trips: 296
    9. Emission: NOx 75 mg/Nm3
    10. Efficiency: 34.56%
  3. Additional Equipment
    1. Kawasaki ammonia de-oxidation method
    2. DLN combustor technology
    3. EV type burners
    4. Miscellaneous spare parts