This offering comprises two complete Siemens-based combined cycle power plants (CCPP), each rated at 21 MW, for a total installed capacity of 42 MW.
Quantity: 2 complete power plants.
The heart of each plant is the high-efficiency Siemens SGT-400 DLE gas turbine rated at 15 MW, coupled with a steam cycle using a C5-3.7/1.2 steam turbine and QF-J6-2 generator delivering an additional 6 MW.
Both units are fueled by natural gas and configured for 50 Hz operation at 10.5 kV.
Each power island includes a XEMC TFW15-2 gas turbine generator, HRSG (heat recovery steam generator), Allen Gears gearbox, advanced lubrication and cooling systems, and full control and electrical infrastructure.
This turnkey solution is ideal for industrial operations or utility power generation requiring rapid deployment and proven technology.
OEM: TBA/various.
Availability (lead time): 0-2.
Specifications
Plant type: combined cycle power plant (CCPP)
Total combined output: 42 MW (2 × 21 MW)
Gas turbine model: Siemens SGT-400 DLE
Model number: Siemens SGT-400 DLE
Year of manufacture: 2017
Frequency: 50 Hz
Rated voltage: 10.5 kV
Gas turbine output: 15 MW per unit
Steam turbine model: C5-3.7/1.2
Steam turbine generator: QF-J6-2 (6 MW)
Steam turbine output: 6 MW per unit
Gas turbine generator: XEMC TFW15-2
Gearbox: Allen Gears
Fuel type: natural gas
Output power: 35 MW
Output power: 35 MW
Speed: 9,500 rpm
Number of shafts: 2 (twin-shaft)
Turbine cycle: combined cycle operation
Design specification: combined cycle operation
Operation continuous intermittent: designed for continuous operation
Insulation class: Class F
ISO 15926 pt 4: 7686
Test medium: air or natural gas
Test pressure: typically 30 bar
Operating Environment and Explosion Protection
Normal operating temperature: 15°C to 40°C
Lower limit operating temperature: -10°C
Upper limit operating temperature: 40°C
Explosion protection gas group: Group II
Explosion protection temperature class: T3
Explosion protection zone: Zone 1
Condition
The equipment was manufactured in 2017 and has seen limited usage with only 16,072 operating hours and 101 starts.
Operating hours: 16,072 hours
Number of starts: 101
Included Major Systems
The integrated water treatment plant, steam tank, fire protection system, high/low voltage cabinets, MCC, and all necessary balance of plant (BOP) equipment are included.
Gearbox unit
Alternator
Cooler system
Lubrication system
Exhaust chimney
Tube system
HRSG (heat recovery steam generator)
Steam tank
Water treatment plant
Control room system
Power transformer
Fire fighting system
High voltage cabinet
Low voltage cabinet
Motor control center (MCC)
High voltage compartments
Request a Quote
✓
Request sent
Thank you, our team will reply to you shortly.
Direct access to our team
Email American Plant & Equipment
Tell us what you want to buy, source, finance, or sell. A machinery specialist will follow up with you.
✓
Thank you. Your request is with the American Plant and Equipment team.
A machinery specialist will follow up with you.
Machinery updates
Subscribe to our email list
Tell us which industries you follow and we will send you the machines that match.
✓
You are on the list.
We will email you when machines that match your interests come in. Unsubscribe from any message.