GE, TM 2500, 1998, 24 MW, Dual Fuel, Mobile Power Package

Description

  1. Overview
    1. Gas turbine model TM 2500, dual fuel, 60 cycle, 24 MW per unit
    2. Each unit consists of a gas generator and power turbine with a 0 timed overhaul unit installed on package
    3. Total package run hours: 51,000 hours
    4. Unit available in February 2023 and delivered to the port
  2. Trailer Configuration
    1. Three trailers loaded with the components of the gas turbine
    2. First trailer: dimensions 21 meters x 3 meters, includes gas turbine generator, fuel system, lubrication system, electrical equipment and synchronization
    3. Second trailer: dimensions 14.6 meters x 2.6 meters, includes control panel, fire and gas suppression, fuel handling system
  3. Electrical Components
    1. Generator: 13.8 / 11 kV with 32941 MVA capacity, 0.9 PF
    2. Main transformer: 13.8 kV / 11 kV with 32941 MVA capacity
    3. Auxiliary transformer: 13.8 kV / 11 kV / 0.4 kV with 650 kVA capacity
    4. DC charger: 120 V / 63 A and batteries with 100 ampere hour capacity
    5. Earthing system per GE specification
  4. Fuel System
    1. Dual fuel: natural gas and diesel
    2. Station operates with diesel fuel after passing through the fuel handling system
    3. Diesel fuel tanks: 100 cubic meters capacity each, total of 400 cubic meters for raw fuel
    4. Diesel fuel tanks: 100 cubic meters capacity each, total of 200 cubic meters for handled fuel
  5. Fire Suppression System
    1. Water tank and pumps for the transformer and diesel tanks
    2. CO2 extinguishing system for electrical components
    3. Powder extinguishing system for the lubrication system
  6. Washing System
    1. Complete water wash unit with 18.5 cubic meters capacity to wash and purify the diesel used for 1 unit
    2. System includes a wastewater tank for draining
  7. Additional Details
    1. Unit will come with new tires for transport
    2. All ducting is being painted to freshen up the looks