Monberg & Thorsen, Comprimo, Natural Gas Treatment Plant, 10,880,000 m3/day

Description

  1. Overview
    1. Natural gas treatment plant
    2. Capacity of 10,880,000 m³ per day (384,223,000 cfd)
    3. Constructed and designed by Mt-Monberg & Thorsen A/S Copenhagen (now Mt Hojgaard) and Comprimo B.W. Amsterdam (now Worley Comprimo)
    4. Originally built as a back-up plant for an offshore treatment plant, typically used 15 days per year during offshore plant maintenance, occasional operational standby testing, and to process
  2. Components
    1. Natural gas treating/sweetening unit
    2. Natural gas drying unit
    3. Natural gas chilling system
    4. Condensate stabilization unit
    5. Hydrogen sulfide incinerator unit
    6. Including piping, pumps, sensors, valves, and additional infrastructure
  3. Condition
    1. Used
  4. Specifications
    1. Stock number: 48962018