Tetra Pak, TBA 8 V110, 2001, 1000ml Square Brik, Helicap 27, Filling Line

Description

  1. Overview
    1. Tetra Pak TBA8 1000ml square V110, Helicap 27
    2. Brand: Tetra Pak
    3. Model: TBA 8 V110
    4. Year: 2001
    5. Machine hours: 26,000 h
    6. Product types: dairy
    7. Containers: Brik
    8. Formats: 1 L (0.3 gal)
    9. This used bottling line is configured around a Tetra Pak TBA 8 V110 filling machine for square 1.0L Brik carton packs. Manufactured approximately in 2001, the filling machine has approximately 26,000 working hours and received a total refurbishment in 2026. The line includes dedicated screw-cap application, wrap-around tray packing and interconnecting conveyor equipment for an integrated carton packaging process.
  2. Machines List
    1. Machine type: filling machine
    2. Brand: Tetra Pak
    3. Model: TBA 8 V110
    4. Year: 2001
    5. Square 1.0L Brik carton format; total refurbishment in 2026; approximately 26,000 working hours
    6. Machine type: capping machine
    7. Brand: Tetra Pak
    8. Model: TCAP 45
    9. Modified for Helicap 27; pre-punched paper; screw cap
    10. Machine type: conveyors
    11. Approximately 30 metres; according to standard layout
    12. Machine type: wrap around packer
    13. Brand: Tetra Pak
    14. Model: TCBP 70
    15. For wrap-around tray
    16. Wrap around packer
  3. Technical Specifications & Performance Data
    1. Filling machine: Tetra Pak TBA 8 V110
    2. Pack format: square Brik carton, 1.0L
    3. Year of manufacture: approximately 2001
    4. Working hours: approximately 26,000 h
    5. Refurbishment: total refurbishment in 2026
    6. Conveyors: approximately 30 metres, according to the standard layout
  4. Advanced Automation & Control Systems
    1. The line combines filling, cap application, conveying and tray packing into a coordinated industrial packaging arrangement. The Tetra Pak TCAP 45 cap applicator is modified for Helicap 27 screw caps and operates with pre-punched paper, supporting the specified carton closure configuration. The conveyor system provides product transfer between the principal operating stations.
    2. Machines of this type are typically operated through dedicated machine controls and coordinated with upstream product preparation and downstream packing equipment. Functional verification, test running and inspection have been performed following refurbishment.
  5. Production Line Integration Capabilities
    1. This complete carton filling and packaging line is designed for handling square 1.0L Brik packs. Its configuration supports a logical process flow from carton filling through screw-cap application, conveying and wrap-around tray packing. It is suitable for industrial packaging and beverage production applications using the stated carton format.
    2. The tray packer is configured for wrap-around tray applications, creating a practical downstream packaging stage for filled and capped carton packs. This arrangement can be considered for second hand carton packaging projects requiring a compact filling-to-secondary-packaging workflow.
  6. Machine Condition & Maintenance History
    1. The machines have been checked and are described as being in excellent condition with Tetra Pak history. The filling machine underwent total refurbishment in 2026, followed by a test run and inspection. Online test runs and final inspection with water-filled packages are available, allowing operational evaluation of the equipment configuration.
  7. Operational Performance & Versatility
    1. The TBA 8 V110 configuration is dedicated to square 1.0L Brik carton handling. The TCAP 45 equipment applies Helicap 27 screw caps, while the TCBP 70 completes the line with wrap-around tray packing. This combination brings filling, closure application, product handling and secondary packaging together for carton-based production operations.
  8. Installation Requirements & Site Preparation
    1. Installation planning should accommodate the approximately 30-metre conveyor arrangement and the required working access around the filler, cap applicator and tray packer. Site preparation for a complete bottling line typically includes coordinated mechanical installation, electrical connection, utility routing, product-feed integration and downstream handling arrangements. The final line layout should be matched to available floor space and the selected carton production flow.
  9. Safety Standards & Compliance Certification
    1. Safe commissioning should include inspection of guards, access areas, emergency-stop functions, conveyor interfaces and operating procedures across the connected equipment. The completed test run and inspection provide a useful basis for acceptance assessment. Installation and operation should be carried out in accordance with applicable local machinery, electrical, food-processing and workplace safety requirements.