NovaStar, CW102, Biomass Fueled Power Plant, 2022, 25 MW

Description

  1. Overview
    1. 25 MW biomass fueled power plant, built 2022, new and unused
    2. 50 Hz, 11 kV
    3. The fuel handling will be designed to accommodate the end user's own fuel
  2. Scope Of Supply
    1. 1 x 105 t/hr (231,000 lb/hr) biomass boiler
    2. 1 x condensing steam turbine-generator (STG) package
    3. 1 x air-cooled condenser (ACC)
  3. Specifications
    1. Year: 2022
    2. Rated output: 25 MW
    3. Frequency: 50 Hz
    4. Voltage: 11 kV
    5. Boiler capacity: 105 t/hr (231,000 lb/hr)
    6. Fuel: biomass; the plant will be designed to accommodate the end user's own fuel
  4. Condition
    1. New and unused; the plant has not been installed or operated
    2. In storage, crated and wrapped, with protective film still on the control cabinet