TT-2177 GAS BASED COMBINED CYCLE POWER PLANT, 116 MW, YEAR 2021
TT-2177 GAS BASED COMBINED CYCLE POWER PLANT, 116 MW, YEAR 2021
GENERAL ELECTRIC GAS TURBINE
GAS TURBINE MODEL NUMBER: GE, 6FAG
QUANTITY: 1
In stock
SKU
TT-2177
REFERENCE NUMBER: TT-2177
GAS BASED COMBINED CYCLE POWER PLANT, 116 MW, YEAR 2021
GENERAL ELECTRIC GAS TURBINE
GAS TURBINE MODEL NUMBER: GE, 6FAG
BRIEF INTRODUCTION
-THE PROJECT IS A 116 MW COMBINED CYCLE GAS BASED POWER PLANT WHICH IS FULLY ERECTED AND READY FOR COMMISSIONING BY 2013.
TECHNICAL DESCRIPTION OF THE PLANT
PLANT CONFIGURATION
CONFIGURATION: 1GT+ 1HRSG+ 1 ST
GAS TURBINE MODEL NUMBER: GE, 6FAG
GAS TURBINE OUTPUT AT ISO CONDITIONS: 78.595 MW
GAS TURBINE OUTPUT AT SITE CONDITIONS: 71.727 MW
HRSG MODEL: UNFIRED
GROSS COMBINED CYCLE OUTPUT: 116 MW (AT ISO)
GT GROSS LHV HEAT RATE: 10216 KJ/KWH
GROSS COMBINED CYCLE HEAT RATE: 6838 KJ/KWH
[CONVERSION 1 KJ = 0.239006 KCAL/KWH]: [1634.3 KCAL/KWH]
STEAM TURBINE OUTPUT: 37.6 MW
LHV GROSS EFFICIENCY: [860 (KCAL REQUIRED TO GENERATE 1 KWH] /1634.3 = 52.65%]
PARAMETERS USED FOR PLANT
SITE ALTITUDE: 31.5 M
SITE PRESSURE: 1013 MBAR
AMBIENT DRY-BULB TEMPERATURE: 29°C
AMBIENT RELATIVE HUMIDITY: 70 %
GRID VOLTAGE: 220 KV
GRID FREQUENCY: 50 Hz
POWER FACTOR: 0.8 LAGGING, 0.95 LEADING (SUBJECT TO DETAILS FROM VENDOR)
FUEL: NATURAL GAS
GAS TURBINES: GENERAL ELECTRIC, TYPE 6FAG, AXIAL EXHAUST, GAS TURBINE GENERATORS: BRUSHLESS, 50 Hz, STARTING STATIC FREQUENCY CONVERTER. BY PASS STACK GENERATOR ENCLOSURE: OUTDOOR WITH ACOUSTIC ENCLOSURE COMPRESSOR CLEANING: OFF-LINE COMPRESSOR WATER WASH OPERATING MODE: BASE LOAD
HRSH: 2 PRESSURE SYSTEMS. UNFIRED, NATURAL CIRCULATION, OUTDOOR
STEAM TURBINE: CONDENSING, DOUBLE FLOW EXHAUST -AXIAL EXHAUST, GENERATOR: STATIC OR BRUSHLESS, 50 Hz, ENCLOSURE: INDOOR
MAIN COOLING SYSTEM: CLOSED LOOP COOLING WATER SYSTEM USING AN INDUCED DRAUGHT COOLING TOWER, DEMATERIALISED WATER SYSTEM
SWITCHYARD: 220 KV, 50 Hz
PLANT CONTROL PHILOSOPHY: AUTOMATIC START-UP & SHUTDOWN, AUTO/MANUAL CONTROL REMOTE DISPATCHING
GAS SPECIFICATIONS
CONSTITUENT - PERCENT BY VOLUME
METHANE (CH4): MINIMUM 85.0: MAXIMUM 100.00
ETHANE (C2H6): MINIMUM 0: MAXIMUM 6.00
PROPANE (C3H8): MINIMUM 0: MAXIMUM 5.00
BUTANE (C3H8): MINIMUM 0: MAXIMUM 3.00
PENTANE (C5H12) AND HIGHER: MINIMUM 0: MAXIMUM 2.00
HYDROGEN SULPHIDE (HS2): MINIMUM 0: MAXIMUM 0
CARBON DIOXIDE (CO2): MINIMUM 0: MAXIMUM 2.00
NITROGEN: MINIMUM 0: MAXIMUM 3.00
OXYGEN (O2): MINIMUM 0: MAXIMUM 1.00
INERT (THE TOTAL COMBINED NITROGEN, OXYGEN, CARBON DIOXIDE AND ANY OTHER INERT COMPOUND): MINIMUM 0: MAXIMUM 5.00
MAJOR EQUIPMENT DETAILS
GENERAL ELECTRIC GAS TURBINE
SNM STEAM TURBINE
TDPS
THEMAX HRSG
ABB BOILER FEED WATER PUMPS
TOSHIBA (VIJAY ELECTRICALS) STEP UP TRANSFORMERS
ALSTOM GENERATOR CIRCUIT BREAKER
SCHNEIDER ELECTRIC MV SWITCHGEARS
GENERAL ELECTRIC GAS COMPRESSORS
MIL (KSB)STEAM BYPASS VALVES
MATHER & PLATT FIRE PUMPS
B&W SPIG COOLING TOWER
INGRESSOL RAND AIR COMPRESSOR
GRIP ENGINEER PVT LTD CRANE AND HOIST
GE (ALSTOM) ISOLATED PHASE BUS
TOSHIBA (VIJAY ELECTRICALS) UNIT AUXILIARY TRANSFORMER
GE (ALSTOM) DISTRIBUTED CONTROL SYSTEM
NIRMAL INSDUSTRIES CONTROLS PVT LTD FUEL GAS SYSTEM
QUANTITY: 1